Grace Jean, Washington, DC – IHS Jane's Defence Weekly
07 August 2014
The US Navy's 11th Virginia-class attack submarine, North Dakota (SSN 784), prepares to head out from General Dynamics Electric Boat based in Groton, Connecticut, for its 'alpha' sea trials on 3 August 2014. Source: General Dynamics Electric Boat
Key Points
North Dakota (SSN 784) is conducting 'bravo' sea trials in the Atlantic
The 10-day test is intended to bring the boat closer to handover and commissioning on 25 October
The US Navy's (USN's) first Virginia-class attack submarine to be built with a redesigned bow has departed on its second ocean voyage for an extended set of sea trials, shipbuilder General Dynamics Electric Boat (GDEB) told IHS Jane's on 6 August.
North Dakota (SSN 784) had returned to GDEB's facility in Groton, Connecticut, on 5 August after successfully completing its first ocean voyage, known as 'alpha' sea trials. The two-day at-sea period occurred nearly four months after officials publicly disclosed materiel issues associated with the bow's redesign, which prompted the navy to delay the boat's 31 May 2014 commissioning date.
North Dakota is moving swiftly with testing, as evidenced by the effort to turn the boat back out for its 'bravo' sea trials less than 24 hours after it had returned from 'alpha' trials, GDEB spokesman Greg Rose told IHS Jane's . During the 'alpha' sea trials, the boat submerged for the first time and conducted a spectrum of submarine- and propulsion plant operations, to include high-speed runs, both on and below the surface, to demonstrate mission capability.
North Dakota (SSN 784) – the US Navy's first Virginia-class attack submarine with a redesigned bow – sails down the Thames River in Groton, Connecticut, en route to its first ocean voyage. (General Dynamics Electric Boat)
The 'bravo' trials, which are expected to run for 10 days, will test the boat's endurance, and continue with other tests, he said.
North Dakota was expected to have been handed over to the navy by the end of August, according to the 66-month build contract agreement. GDEB's Rose declined to specify a handover date, but said: "We're on track. Based on past performance, we feel like we're in good shape to make that."
If all goes as planned, North Dakota is to be commissioned on 25 October 2014, Naval Sea Systems Command (NAVSEA) told IHS Jane's on 6 August.
As the lead boat in the USN's third batch of nuclear-powered Virginia-class submarines, North Dakota and the rest of the 'Block III' boats feature a new bow design that was part of an affordability effort to drive down programme costs and reduce ship construction time.
The USN intends to acquire a 30-boat class of Virginias and expects to sustain current procurement plans of two Virginia-class boats per year for about USD2 billion per boat.
GDEB is constructing the boats in partnership with Huntington Ingalls Industries Newport News Shipbuilding in Virginia. The two shipbuilders have delivered 10 boats, all of which are in service, and are working on eight additional submarines.
Discover more from JC's Royal New Zealand Navy, World Navies, Military News, Lighthouses and other Marine News-